Delivery Process Project Data Project Planning
Instructions
The following table has data regarding several activities associated with the implementation of a new delivery process for a new retail chain. The contract with the new retail chain states that starting on the 13th day from now, your firm will experience a penalty of $110 per day until the job is completed. Indirect project costs amount to $227 per day. The data on direct costs and activity precedent relationships are given in the table.
Delivery Process Project Data | |||||
Activity | Normal Time (Days) | Normal Cost Per Day | Crash Time (Days) | Crash Cost Per Day | Immediate Predecessor(s) |
A | 4 | $1,004 | 3 | $1,232 | None |
B | 7 | $1,411 | 4 | $2,032 | None |
C | 5 | $2,020 | 4 | $2,707 | None |
D | 6 | $1,263 | 5 | $1,472 | A |
E | 3 | $915 | 2 | $1,166 | B |
F | 11 | $2,517 | 6 | $3,757 | C |
G | 4 | $812 | 3 | $1,431 | D, E |
H | 3 | $394 | 1 | $500 | F, G |
To complete this assignment, answer the following questions. Begin by drawing the project network diagram. A start node and end node are suggested.
Requirements
In order to successfully complete this assignment, you must:
- Make few or no grammatical, spelling, or syntactical errors.
- Show any or all of the following:
- Critical thinking
- Original thinking
- Researched examples
- Critical/original thinking: Demonstrate new approaches and/or ability to “push back” rather than simply reproducing another’s thoughts
- Use direct quotations sparingly and judiciously
- Properly identify any sources and integrate into own thoughts and ideas
- Provide a straightforward, easy-to-follow arrangement with appropriate formatting:
- Comply with APA format
- Answers clearly marked and named within assignment file(s)
- Create a Word document and name it using the following convention: “YourName-M2-assignment”
- On the Word document, answer the prompts listed above in no more than five pages, exclusive of title page, executive summary, and bibliography
- You can use the drawing tools in Word to create your project network diagram. Alternatively, you may hand draw the project network diagram and scan/photograph it and paste it into the document.
- Any charts and graphs you use for the paper may be appropriately sized to allow for adequate room for your text and should be in your paper, not in a separate file
- Upload the document to this page by clicking the “Submit Assignment” button